Analysis of The Effect of Fabrication and Installation Work on Cost Overruns in Steam Turbine Generator Projects and Coal Boilers in Palembang
DOI: 10.35870/ijmsit.v2i2.629
Jenni Ria Rajagukguk, Kudus Yallbert
Article Metrics
- Views 0
- Downloads 0
- Scopus Citations
- Google Scholar
- Crossref Citations
- Semantic Scholar
- DataCite Metrics
-
If the link doesn't work, copy the DOI or article title for manual search (API Maintenance).
Abstract
Delays (time overruns, SPI < 1) and exceeding budget costs (cost overruns, CPI < 1) on EPC (Engineering, Procurement, Construction) Projects are a global phenomenon due to the very diverse and unique nature of construction projects so that many companies experience losses during construction execution work activities. A very critical job in the execution of EPC projects is fabrication and installation activities which are part of construction activities because there are very many variables that have an impact on cost overruns if the fabrication and installation work is not monitored and controlled properly. In this study, an analysis of the effect of fabrication and installation work on cost overruns was carried out on the Steam Turbine Generator and Coal Boiler Project in Palembang. The analysis was performed using SPSS Ver software. 25 by processing questionnaire data from the answers of 42 respondents. With good control and early anticipation of construction activities so that it can help project managers in managing projects more effectively and efficiently so that the SPI (Schedule Performance Index) and CPI (Cost Performance Index) are more than one and the achievement of other requirements in accordance with project specifications and contracts.
Keywords
No keywords available.
Article Metadata
Peer Review Process
This article has undergone a double-blind peer review process to ensure quality and impartiality.
Indexing Information
Discover where this journal is indexed at our indexing page to understand its reach and credibility.
Open Science Badges
This journal supports transparency in research and encourages authors to meet criteria for Open Science Badges by sharing data, materials, or preregistered studies.
How to Cite
Article Information
This article has been peer-reviewed and published in the International Journal of Management Science and Information Technology. The content is available under the terms of the Creative Commons Attribution 4.0 International License.
-
Issue: Vol. 2 No. 2 (2022)
-
Section: Articles
-
Published: %750 %e, %2022
-
License: CC BY 4.0
-
Copyright: © 2022 Authors
-
DOI: 10.35870/ijmsit.v2i2.629
AI Research Hub
This article is indexed and available through various AI-powered research tools and citation platforms. Our AI Research Hub ensures that scholarly work is discoverable, accessible, and easily integrated into the global research ecosystem. By leveraging artificial intelligence for indexing, recommendation, and citation analysis, we enhance the visibility and impact of published research.
-
Alaa Khalfan, Alaa Khalfan Al Ghaithi, Rafeeq Ameen Kattiparuthi, 2017, Alaa Moosa Koya Diterbitkan Juli 2017, Delay Analysis in EPC Projects using Ishikawa Diagram International Journal of Advanced Engineering, Management and Science (IJAEMS), [Vol-3, Issue-7, July-2017]https://dx.doi.org/10.24001/ijaems.3.7.7ISSN: 2454-1311
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Nida Azhar, Rizwan U. Farooqui and Syed M. Ahmed , 2008, Cost Overrun Factors In Construction Industry of Pakistan, First International Conference on Construction in Developing Countries (ICCIDC-I), Advancing and Integrating Construction Education, Research & Practice, August 4-5, 2008, Karachi, Pakistan, 499-508.
-
Dani Prabowo (2018), https://properti.kompas.com/read/2018/09/13/091659821/ indonesia- kuasai-60-persen-pasar-konstruksi-asean
-
Etikaf Hussain, Muhammad Umer, Rizwan U. Farooqui and Sorosh Lodi 2012, “Factors Affecting Construction Cost in the Pakistani Construction Industry, Third International Conference on Construction in Developing Countries (ICCIDC-III), Advancing Civil, Architectural and Construction Engineering & Management, July 4 -6,2012, Bangkok, Thailand.

This work is licensed under a Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License.
Authors who publish with this journal agree to the following terms:
1. Copyright Retention and Open Access License
Authors retain copyright of their work and grant the journal non-exclusive right of first publication under the Creative Commons Attribution 4.0 International License (CC BY 4.0).
This license allows unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
2. Rights Granted Under CC BY 4.0
Under this license, readers are free to:
- Share — copy and redistribute the material in any medium or format
- Adapt — remix, transform, and build upon the material for any purpose, including commercial use
- No additional restrictions — the licensor cannot revoke these freedoms as long as license terms are followed
3. Attribution Requirements
All uses must include:
- Proper citation of the original work
- Link to the Creative Commons license
- Indication if changes were made to the original work
- No suggestion that the licensor endorses the user or their use
4. Additional Distribution Rights
Authors may:
- Deposit the published version in institutional repositories
- Share through academic social networks
- Include in books, monographs, or other publications
- Post on personal or institutional websites
Requirement: All additional distributions must maintain the CC BY 4.0 license and proper attribution.
5. Self-Archiving and Pre-Print Sharing
Authors are encouraged to:
- Share pre-prints and post-prints online
- Deposit in subject-specific repositories (e.g., arXiv, bioRxiv)
- Engage in scholarly communication throughout the publication process
6. Open Access Commitment
This journal provides immediate open access to all content, supporting the global exchange of knowledge without financial, legal, or technical barriers.